So I can't get any of the fixes (1, 2, 3) I've seen working on RStudio for changing the units of the x axis to days, weeks or months. I dont know how to get this option to work.
Example:
library(DiagrammeR)
mermaid("
gantt
title Gantt
dateFormat DD-MM-YYYY
axisFormat %d/%m
section One
Task One : 07-05-2019, 7d
Task Two : 09-05-2019, 7d ")
It just shows a white window with black text instead of a normal gantt chart.
Without the axis part, it runs just fine.