When using Jira, how do I ensure each team member has enough work in a sprint?

325 views Asked by At

While doing planning sessions using Rapid Board what are some reasonable ways to make sure each person on the team has a decent enough amount of work for the length of the sprint?

e.g. if you have 10 people on the team, how can you quickly see if 1 person only has 2 hours worth of work? Are you supposed to wait for them to speak up or can this be done through Greenhopper somehow?

2

There are 2 answers

3
Assaf Stone On BEST ANSWER

The best way to make sure that everybody has work to do throughout the sprint, is to let them sign up for work every time they complete the previous task. This means that the members will be "pulling" work, rather than having their work "pushed" onto them.

If you conduct a daily scrum - daily - you will find out pretty quickly that someone is not signing up for new work - that he's either stuck on what he has, or not picking new work. Essentially, if you break up your work into small enough tasks, you will know what is going on within a day.

All this will work for you regardless of which software tool you use to track your sprint.

0
Michael W On

If you are using Jira, (and your project can afford it) I would suggest looking into the add-on "Green Hopper." It is also made by Atlassian and does a lot of what you are asking for. You can view individuals and see how much work they have as well as how much free time is remaining.

You can also drag the stories (Jira issues represented as virtual index cards) into different iterations (sprints) and onto different people. As well, it will help you to run your daily standup (using it as the scrum board), however YMMV.