Argo Rollouts - How to abort/rollback canary rollout

836 views Asked by At

I'm working on a POC for Argo Rollouts and all is good for rolling out an application. However my rollback testing is a bit confusing. When I abort the rollout the canary get successfully ScaledDown, however the overall rollout status is set to degraded.

When I attempt to undo the rollout an error failed restoring revision 0

Anyone have an suggestions about what the issue might be or how to debug it?

1

There are 1 answers

0
Francisco Cardoso On

After aborting a rollout, it's normal to be in degraded status. It only means that next step is updating your spec back to the stable version.